For anything bigger than a small repair, paying the whole price at the end is hard on the trade, and paying it all at the start is risky for you. Stage payments split the difference: the price is broken into parts, and each part is paid when that part of the work is done.
What a stage payment is
A stage is a chunk of the job you can point at when it's finished: "strip-out done", "first fix done", "roof on". Each stage has its own price, agreed before the job starts. When a stage is complete, you check it, and then you pay for it.
The key is that payments follow finished work, not dates. "£2,000 on the 1st of the month" can fall due whether or not anything has happened. "£2,000 when the walls are plastered" can't.
Why it works for both sides
- For you: you're never far ahead of the work. If something goes wrong, the money you've paid matches what's been done.
- For the trade: they're not buying materials and paying wages for weeks before seeing any money. That's why a reasonable deposit isn't a red flag.
- For both: agreeing the stages up front forces a clear conversation about what the job actually involves.
How much should the deposit be?
A deposit of around 10 to 20 per cent is common, especially where materials have to be bought or ordered. A larger deposit can be reasonable for something made to order, like a kitchen or bespoke windows, but ask what it's for and ask for the supplier's order confirmation.
Be wary of anyone who wants half or more before they've started, or who asks for a large payment in cash.
Typical stages for common jobs
Every job is different, but these give you a starting point.
A bathroom refit
| Stage | When it's paid |
|---|---|
| Deposit | When you accept the quote, towards materials |
| Strip-out and first fix | Old suite out, new pipes and cables in place |
| Boarding, tiling and fitting | Walls and floor done, suite fitted |
| Finish | Everything working, sealed, cleaned up and signed off |
A single-storey extension
| Stage | When it's paid |
|---|---|
| Deposit | When you accept the quote |
| Foundations | Dug, inspected where needed, and poured |
| Walls | Built up to roof level |
| Roof on | Wind and watertight |
| First fix and plastering | Pipes and cables in, walls plastered |
| Second fix and finish | Kitchen or fittings in, decorated, signed off |
Extensions usually need a building warrant, and the council may inspect at certain points. It makes sense to line stages up with those. See do I need a building warrant in Scotland?
OnBelt lays quotes side by side, in stages, with VAT shown, and keeps the whole job in one place. It’s coming soon.
Get early accessSigning a stage off
Before you pay for a stage, look at it. Photos help: ask for pictures of anything that will be covered up, like pipes and cables before the walls are boarded. If you're not happy with something, say so before you pay, and agree what will be done about it.
Holding a little back at the end
On larger jobs, it's common to agree that a small part of the price is paid a few weeks after completion, once any snags have been sorted. This is sometimes called a retention. Agree it at the start, and write down how long it's held and what releases it, so it doesn't feel like a surprise.
When the job changes
Most jobs change a little once they're opened up. The fair way to handle it is simple: every change is priced and agreed in writing before the extra work starts. Add it to the stage it belongs to, so the payment plan stays accurate.
How to pay
- Pay by bank transfer, so there's a record of every payment.
- Keep the quote, the stages and every agreed change together.
- If your trade says their bank details have changed, phone them on a number you already have before you pay. Changed-bank-details scams are common.
If something goes wrong
Start by talking, then put your concerns in writing. Under the Consumer Rights Act 2015, a trader must do the work with reasonable care and skill. If they haven't, you can ask them to put it right, or in some cases ask for a price reduction. In Scotland, Consumer Advice Scotland can explain your options.
How OnBelt handles stages
On OnBelt, every quote is split into stages, each with its own price, and VAT is shown. Stages are signed off from photos, and if the job changes, the extra is agreed in the app before it starts. You pay your trade directly; the app keeps the record of what was agreed and what was signed off.
Frequently asked questions
How much deposit should I pay a builder?
Around 10 to 20 per cent is common, more for made-to-order items like a kitchen. Ask what the deposit pays for, and be wary of requests for half or more before work starts.
Should I pay a tradesperson in cash?
A bank transfer is better: it gives you a clear record of what you paid and when. Be cautious of discounts offered for paying in cash.
What is a retention?
A small part of the price that's paid a few weeks after the job is finished, once any snags are fixed. Agree the amount and the timing at the start.
Can I stop paying if I'm unhappy with the work?
Raise it straight away and put it in writing before the next payment is due. Agree what will be fixed and when. Withholding money without explaining why usually makes things worse, so keep a clear record of the problem.